Timeline for Getting a New Stationary Generator Up and Running

Even though power outages are a constant source of disruption and irritation in our lives, they nevertheless occasionally occur. This is especially relevant now that California is experiencing an increase in fires. Another thing the severe winter of 2022–2023 taught us is that there are threats all year long.

Even during PG&E's public safety power shutdown events, you need a reliable electrical supply if you wish to prevent these unplanned outages. This holds significance not only for residential dwellings but also for commercial establishments and enterprises. Long-term cost savings can be achieved by investing in generators since they minimise downtime. They are an excellent fallback in the event of unexpected power disruptions.


From our sites in Sacramento and the San Francisco Bay Area, we sell generators all over Northern California. For further information, call +1 (916) 668-0605.

Timeline for Getting a New Stationary Generator Up and Running

Generators come in two primary varieties: towable and stationary. This post will discuss stationary generators and the estimated time needed to choose, order, and install one at your location.

A specialist with the requisite competence for a project such as this is needed to install a new stationary generator. Even for the average handyperson, this is definitely not something they can figure out on their own.[Revised for lead times in 2023] Now let's examine a one-year and two-year plan. Although a year might seem like a long time, keep in mind that there are circumstances in which it may take longer.

Month 1: During the first two months, you and an engineer will work together to create and polish a detailed plan that you will present to the city building department for approval.

Month 2: Days 2 through 5 Months 3 through 6: Depending on the backlogs they must clear, expect the city's engineering and other agencies to examine and approve your plan in two to three, four, or six weeks each. The requirements are stricter for larger stationary generators.

They flow out in a continual torrent of change at every level. It's likely that since you had your previous generator installed, the rules governing its location and use have changed. Even the position of your current generator might not meet today's regulations for being set off from a structure, particularly in terms of how close it is to windows. An air quality permit is also required. You can complete the purchase and start site preparations as soon as your plan is approved.

Weeks 6 through 9 Months 7 through 18: After placing your order, you need allow at least 4 months for the stationary generator to be delivered.

Weeks 10 and 11 Months 19 through 22: After the delivery, more work needs to be done. It takes time for installation, extra electrical work, startup, and testing.

Month 12: Testing will be necessary to ensure compliance with all regulatory requirements from Months 23 to 24.

One thing to bear in mind is that this schedule's timeline is subject to change. This implies that, depending on the situation, your experience can be shorter or longer. Although the installation procedure can take several months or more, it is generally expected that everything will be finished within a year.

What Some Organizations are Doing to Prep for Backup Power

We occasionally assist our clients in implementing their backup power plan in two phases. We're directing them towards:

  • Set up an ATS, or automatic transfer switch.
  • prepare the location by pouring the concrete pad, for example.
  • In the event of a power outage, reserve one of our towable generators for their usage.

They are currently following the steps mentioned in this post to have their stationary generator operational in time for the fire season of the next year.

Next up, what?

Join together with Generator World, a business that can assist you at every turn. We will assess your demands up front and assist in choosing the appropriate generator type, size, and brand. After that, we'll collaborate with you to successfully navigate the regulatory obstacles unique to your area and choose reliable contractors to complete the job.